Set of departments which facilitate the development function include:
Architecture Workshop, Engineering, Civil Works, Electrical, Planning, Co-ordination Cell, Quality Assurance, Quality Controls and Site Administration. All of these in-house departments ensure collectively the cohesive effort required to develop and deliver a successful project.
Sr# | Activity | Department |
---|---|---|
1 | Feasibility Study of Land For Project | Engineering |
2 | Land Acquisition | Land & Legal |
3 | Topo Graphic Survey The survey reflects
|
External Services |
4 | Tentative Reconanse Survey Geological Survey and Hydrological Features
|
Engineering |
5 | Layout Generation And Master Plan | AW |
6 | IEE Report Initial Environmental Examination (IEE) for the propose project will be in accordance with
|
Engineering |
7 |
Preliminary Planning (Infrastructure)
|
AW + Engineering |
8 | Project Cost Evaluation Project cost and its financial viability |
Engineering + P.C.C |
9 | Detail Layout Plan | AW |
10 | Detailed Planning and Engineering Design Preparation of detailed infrastructure design reports for approval from the concerned Government Agencies. |
AW + Engineering |
11 | Project Execution Detailed layout plan and detailed engineering drawings are issued to site for their execution along with intimation to the concerned department regarding commencement of work and their physical progress achieved. |
Engineering |
12 | Booking and Sale of Project | Sales & Marketing |
13 | Houses Development | All concerned Departments |
14 | Houses Handing Over to Customer | Sales & Marketing |
15 | Maintenance of Project | AW + Engineering |